Before the valve is shipped all connections
(flanges or weld connection.) are covered with plastic caps. This way the valve
internals are protected against the ingress of dirt and damage. Before the
valve is installed these covers must be removed. After a visual inspection on
possible shipping damages and eventual presence of dirt/solids the valve can be
installed in the direction of the arrow. The DATIAN series PSG are very
maintenance friendly. The only maintenance required is the exchange of the
soft-parts and the cleaning of the internals during the annual inspection and
the exchange of springs every 3-5 years depending on the operating conditions.
Other parts only have to be exchanged when they are damaged or when there are
changes in process conditions.
Before inspection and assembly the complete
valve must be cleaned, especially the contact- and guiding area’s of the valve
internals. Soft parts must be exchanged with every inspection. Inspections that
are part of a revision plan are customer responsibility.